Denial to give additional power applied by the consumer –P/395/2013 – P.A.Anthru, Ernakulam.
The consumer had applied for additional power for his industrial firm and the KSEB refused to give the load applied as the consumer has to avail a HT connection for having exceeded his load above the LT limit of 100 KVA. The petition has been disposed of by directing the respondent to allot the load to the consumer within the permissible capacity of the transformer and within the limit of contract demand of 100 KVA.