No. P/059/2014, Sri K.T. Paul, Ernakulam
The appellant is an HT industrial consumer with consumer No. LCN 29/6482 under Electrical Section, Kuruppampady. He was made to remit Rs. 5,40,000/- on 03-09-2011 as transmission charges in order to execute the HT agreement to avail the connection with a load of 400 kVA. The appellant approached the CGRF on 31-03-2014 challenging the authority of the respondents to collect such transmission charges. The respondent submitted before the Forum that the Hon’ble High Court, vide judgment dated: 30-06-2014 in WA1042/2013, had upheld the realization of “transmission development charges”. After hearing both parties, the CGRF held that collection of Transmission Development Charges from the appellant was in order. Aggrieved against the said order, this appeal petition was filed. The appeal petition is disposed of as not pressed.