| The appellant  has paid  required  cost  for  the  work  with  regard  to  obtaining  service connection with a support post. The distribution  licensee  had  effected  the  connection by using PVC weatherproof wire with support pole from the nearby LT post through a narrow path way used by the three consumers including the appellant by avoiding property crossing, since the petitioner failed to produce the consent from the owner of nearby  property.
The appellant filed a request to refund the amount paid by him as ECSC for providing service connection using support post, since casuarina wood log was used for giving the new service connection instead of a WP support post was not used for giving the service connection.  After the completion of the construction works, the appellant filed a petition before CGRF, Southern Region, for getting the refund of the amount paid as a ECSC for providing WP support post and the Forum in its order dated 03-02-2022 rejected the petition.  Aggrieved by the decision of the Forum, the appellant filed the appeal petition.
1.	The	Order	of CGRF, Kottarakkara  dated  03.02. 2022  in  OP No.63/20211 is quashed.
2.	The new support post erected for effecting service connection shall be dismantled & removed at the licensee's cost and KSEB Ltd.  shall  effect supply from the existing post by making use of a suitable side cross arm for maintaining safety and avoiding property crossing.
3.	Th e  consumer   shall  bare   the  cost  of  the  cross  arm  as  necessitated   by KSEB Ltd for effecting the supply.
4.	The amount  collected by KSEB Ltd for the erecting the new  support  post shall be  adjusted  towards  the  cost  of  the  required  cross  arm  and  the balance  shall  be  refunded to the consumer. |  | 
      