The consumer had applied for additional power for his industrial firm and the KSEB refused to give the load applied as the consumer has to avail a HT connection for having exceeded his load above the LT limit of 100 KVA. The petition has been disposed of by directing the respondent to allot the load to the consumer within the permissible capacity of the transformer and within the limit of contract demand of 100 KVA. |
![]() ![]() |
|
The consumer was served with arrear notice towards the dues of electricity consumed more than 10 years ago. It is held that the non payment of ten or more intermittent months old bills is unusual and issuance of notices for dues after a long period is highly unjustifiable. The case disposed in favour of the consumer. |
![]() ![]() |
|
Short assessment bills were issued, being the differential amount of the tariff rates, due to change of tariff of two electric connections from industrial to commercial. The purpose or activity of the consumer is related with the Hall marking of Bullion products. The question to be decided is, ‘whether the activities of the appellant in the premises come under industrial or commercial tariff. The electrical energy is used for business nature and hence upheld the change of tariff but the arrear period is limited to two years, as there was negligence on the part of the KSEB in fixing the eligible tariff. |