The review respondent herein had earlier approached this Authority by filing
an appeal petition against the order passed by the CGRF Central in Complaint No.
CGRF–CR/Comp.12/13-14 dated: 23-07-2013. While disposing the above petition it
was directed to test the existing meter in the review respondent’s premises and
replace it with a new one if the existing one is found faulty. Further the faulty
period may be reassessed with effect from 13-08-2012 to the date of change of meter
based on 6 months subsequent average after the installation of new meter. Now the review petitioner contends that if the above dictum is applied, considerable injury will be resulted to KSEBL. Hence they filed this review petition. The faulty period may be reassessed with effect from 13-08-2012 to the date of change of faulty meter. Excess amount remitted if any may be refunded with interest applicable within a period of 30 days. |
|