The appellant applied for change of ownership in respect of a building which
he purchased by the sale deed dated: 16-02-2011 from Sri Rajan Kunju and Sri
Pradeep Kumar. But, due to the objections filed by Sri Pradeep Kumar, the service
connection was not transferred in the appellant’s name. The appellant approached
the CGRF seeking for transfer of ownership of the service connection in his name
since he submitted all the requisite documents for change of ownership. According
to the respondent, the change of ownership is not registered due to the dispute over
the title and ownership of the property. After hearing both parties the Forum found
that there was no fault or purposeful delay on the part of the respondent in
transferring service connection, since there were series of litigation regarding the
ownership of the building. At the same time the Forum was of the view that the
right of the appellant herein for electric supply could not be delayed in the event of
producing satisfactory proof of his ownership over the building. The CGRF,
therefore, disposed of the petition directing the appellant herein to pursue his
application for service connection on finalisation of the pending dispute regarding the ownership of the property. Aggrieved against the said order this appeal petition
was filed. Respondent is directed to transfer the ownership within a period of 15 days on receipt of application along with required documents. |
|