Downloads
Overview Search Downloads Submit file Up
Category: Orders
Order by: Default | Name | Date | Hits | [Descending]
Orders Files: 1245
Orders of Kerala Electricity Ombudsman  in pdf format
Files:
P-052-2022- Sri. M. Padmanabhan, Palakkad- Order 19-10-22

Download 
Download

The appeal petition relates to the Cheruvathur Traction Substation bearing consumer number 30/8080. There is undue delay in enhancement of Contract Demand of Cheruvathur Traction Substation. The Contract Demand for Cheruvathur Substation is 8 MVA and requested KSEBL to enhance the Contract Demand to 9 MVA during July 2021. As the Licensee has not sanctioned the enhancement of CMD, the appellant is forced to pay the penalty for exceeding the CMD limit at Cheruvathur Traction Substation. The appellant filed petition to CGRF(NR) and CGRF(N) set aside the grievance of the petitioner. The appellant filed appeal petition to this Authority and the decision is taken as follows: (10) The Licensee has to speed up the work of strengthening of Ambalathara-Cheruvathur 110 kV line and complete at the earliest. Sanction the load enhancement on completing this project. (11) The appellant has to take initiative to modify the Traction Distribution System to balance the load in three phase and also to achieve power system stability. (12) The appellant has to conduct a detailed Load Flow Study and assess the distortion and take necessary steps to control these parameters within the permissible limit. (13) The prayer of the appellant regarding the waiver of the penal charges for the maximum demand in excess of contract demand is not permitted.
P-051-2022- Sri. M. Padmanabhan, Palakkad- Order 19-10-22

Download 
Download

The appeal petition is in delay in the enhancement of CMD at Uppala Traction Substation bearing consumer number 30/8392. The Contract Demand of Uppala Traction Substation is 5 MVA and they applied to enhance the Contract Demand to 8 MVA during January 2020. The Traction Substation is receiving power supply in 110 kV at two phase and converting into single phase 25 kV for providing power supply requirement of electric trains. As all the trains were converted into electric trans, the power requirement has increased and hence, the demand increased and applied to the Licensee for the enhancement. Now, the Licensee is charging penalty on excess MD and Railway is paying the penalty when it is legally requested for the enhancement. The appellant filed the appeal petition to this Authority and decision is taken as follows: (14) The Licensee has to make initiative action to complete the doubling of the Transmission line between Konaje – Mancheswaram. The Chief Engineer shall call a meeting of M/s. KPTCL and M/s. Southern Railway and appreciate the importance of this project and impress upon them for an early completion. The enhancement of CMD may sanction accordingly. (15) The appellant shall divert a portion of traction load from Mangalore to Uppala to the newly commissioned substation to reduce the overloading of Uppala. (16) The appellant has to take initiative to modify the Traction Distribution System to balance the load in three phase and also to achieve power system stability. (17) The appellant has to conduct a detailed LFS and assess the distortion and take necessary steps to control these parameters within the permissible limit. (18) The prayer of waiver of penal charges of the excess of contract demand is denied.
P-047-2022-Sri. T.K. Ayyappan, Kollam - Order 16-9-22

Download 
Download

Appellant had filed a complaint at Electrical Section to shift the stay from his property which was installed by the licensee without his consent. The Licensee asked him to remit Rs.34,780/- for shifting the stay wire from the present position to another place of his property. Appellant approached CGRF (SR) and CGRF ordered that the respondent has to execute by collecting only labour charges and the cost of the material, if any, is to be borne by the Licensee. The respondent had revised the estimate to Rs.27,577/- charging only the labour charges. Aggrieved by the decision of the Forum, the appellant approached this Authority and following decisions are taken: 1. The Licensee has to reposition the DP structure by shifting one of the pole to the other side and then shift the stay wire to the side of property with least disturbance to the appellant with immediate effect. 2. The appellant is liable to pay Rs.8,000/- to the Licensee as part of the labour cost for this shifting work. 3. The appellant has to give permission to shift the stay wire to the side of his property or it will be treated as deemed to be consent for the stay wire erection. 4. The order of CGRF, Southern Region, Kottarakkara in OP No. 87/2021 dated 23/06/2022 is modified to this extent.

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday77
mod_vvisit_counterAll4871396