P/121/2017-Sri. Ashokan O.D.

Download 
Download

The Audit team of Regional Audit Officer, Perumbavoor conducted auditing the records of the respondent and found that the consumer was issued with undercharged bills for the months of 09/2013 and 10/2013. Accordingly the appellant was issued with a short assessment bill 28/07/2017 amounting to Rs. 3186/- (Rupees three thousand one hundred and eighty six only). decided to quash the short assessment bill amounting to Rs. 3186/- issued to the appellant. The respondent is directed to revise the short assessment bill by deducting the disincentive Rs.1405/- from the calculation statement and also limit the short assessment of demand charges for a period of 24 months prior to the period from December 2016.
P/119/2017-Sri. Stephan M.M

Download 
Download

The Audit team of Regional Audit Officer, Perumbavoor conducted auditing the records of the respondent and found that the consumer was issued with undercharged bills for the months of 09/2013 and 10/2013. Accordingly the appellant was issued with a short assessment bill on 28/07/2017 amounting to Rs. 5706/- (Rupees five thousand seven hundred and six only). decided to quash the short assessment bill amounting to Rs. 5706/- issued to the appellant. The respondent is directed to revise the short assessment bill by deducting the disincentive Rs.4021/- from the calculation statement and also limit the short assessment of demand charges for a period of 24 months prior to the period from December 2016.
P/103/2017-Sri. George Antony

Download 
Download

Being aggrieved by the demand MG amount, the party approached the CGRF, Ernakulum by filing petition on 20-04-2017 with request to consider the closure of the MG scheme and to refund the sum remitted with interest. the MG amount payable by the consumer shall be dispensed with and the MG amount collected shall be refunded after deducting the portion of the labour charge in the estimate of Rs.466300/- and 10% of administrative expenses of Rs.466300/- towards the construction of 220 metre 11 KV line and erection of 100 KVA transformer.

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday751
mod_vvisit_counterAll4879520