Downloads
Overview Search Downloads Submit file Up
Category: Orders
Page 6 of 427
Order by: Default | Name | Date | Hits | [Ascending]
Orders Files: 1280
Orders of Kerala Electricity Ombudsman  in pdf format
Files:
P/047/2024, The Headmaster, Govt.U.P.School, Nadutheri, Pathanapuram

Download 
Download

The appellant is the Headmaster of Govt.U.P.S, Thalavoor, Kulakkada, Pathanapuram, Kollam Dist., A three phase service connection under the tariff LT 6A has given to this school in the name of Shri. Gangadharan, the Headmaster of the school on 31/03/1977. As the regular power charges are not paid from 03/2004 to 07/2007, the power was dismantled on 18/08/2008. Then the outstanding amount was Rs. 6,045/-. The letter was given to clear the dues on 25/08/2008 and the reminder notice was given on 15/09/2008. No action was taken by the school authorities for clearing the arrears and then the licensee initiated for R.R action. The next notice has been sent to the school on 30/11/2013 for the One time settlement of the outstanding addressing to Shri. Gangadharan, Headmaster the letter was not received by anybody as it is addressed to an individual. Later another letter send on 20/11/2014 was returned. The present headmaster has taken over charge on 29/05/2019 and he had received notice of the dues only on 2023. The appellant has filed the petition to CGRF and CGRF issued order dated 10/06/2024 stating that the appellant is liable to pay arrear bills issued by the licensee. Aggrieved by the order of the CGRF, this appeal petition is filed to this Authority.
P/044/2024, The Secretary, Skyline Oasis Villa Owners Association

Download 
Download

The appellant is the Secretary of the Skyline Oasis Villa Owners Association. The builder named ‘Skyline Builders’ have constructed 30 villas and associated common facilities at Erumpanampady, Thellakam, Kottayam. The builder have availed a temporary connection for the construction purpose under the tariff. LT 7 A. The builder have applied for a connection for powering the common facilities of the villa complex on 02/03/ 2016, under tariff LT 1 A. and the connection was energized on 15/03/2016 under the tariff LT 7A. The builder was regularly paid the power charge and the ownership of the connection was transferred on 10/12/2021 in favour of president skyline oasis villa owners association. The consumer has noted the wrong tariff and requested for tariff change LT 1A on 15/1/2022 and the Licensee has changed the tariff accordingly. The demand of the appellant is to consider the tariff change from the date of connection and refund the excess amount collected from the consumer. The appellant had filed the petition to the CGRF and CGRF issued order dated 04/06/2024 on completing the procedure. Aggrieved by the decision of the CGRF this appeal petition is filed to this Authority.
P/043/2024, Shri.Sarathchandran.M.S

Download 
Download

പരാതിക്കാരനായ ശ്രി. ശരത്ചന്ദ്രൻ , ലൈസൻസിയുടെ കറുകച്ചാൽ ഇലക്ട്രിക്ക് സെക്ഷനിലെ ഒരു ഗാർഹിക ഉപഭോക്താവാണ്. സിംഗിൾ ഫേസ് സർവീസ് കണക്ഷന് 2.91Kw ആണ് കണക്ടഡ് ലോഡ്. പരാതിക്കാരന്റെ വൈദ്യുത മീറ്റർ 18/04/2023 മുതൽ 18/09/2024 വരെ പ്രവർത്തനരഹിതമായിരുന്നു. മുൻ മാസങ്ങളിലെ ആവറേജ് 174 യൂണിറ്റാണെന്നു കണക്കാക്കി ആ കാലയളവിൽ വൈദ്യുത ചാർജ് ഈടാക്കുകയും 24 -08 -2023 ൽ മീറ്റർ മാറ്റി സ്ഥാപിക്കുകയും ചെയ്തു. 10 /2023 ൽ നടത്തിയ ഓഡിറ്റിൽ മീറ്റർ കേടായ സമയത്ത് ഈടാക്കിയ ചാർജ് കുറവാണെന്നും ശരാശരി ഉപഭോഗം 202 യൂണിറ്റാണെന്നും കണ്ടെത്തി. അങ്ങനെ ഒരു ഷോർട് അസ്സെസ്സ്മെന്റ് ബിൽ നല്കിയതിനെത്തുടർന്ന് പരാതിക്കാരൻ CGRF ൽ പരാതി നൽകുകയുണ്ടായി.CGRF ന്റെ ഉത്തരവിൽ ലൈസൻസി നൽകിയ ഷോർട് അസ്സെസ്സ്മെന്റ് ബിൽ അടക്കാൻ പരാതിക്കാരൻ ബാധ്യസ്ഥനാണെന്ന് പറയുന്നു. അതിന്റെ അപ്പീൽ പരാതിയായിട്ടാണ് ഈ പരാതി ഇലെക്ട്രിസിറ്റി ഓംബുഡ്സ്മാൻ സമക്ഷം സമർപ്പിച്ചിരിക്കുന്നത്.

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday2888
mod_vvisit_counterAll5293784