Penalization under Sec. 126 for unauthorized use of energy – P/265/2012 – Subash T., Pathanamthitta

Download 
Download

KSEB detected unauthorized load in the premises of the consumer and served a provisional bill under Section 126 of Electricity Act 2003. The consumer filed objection against the penal bill, before the AE wherein the consumer had stated that he had applied well in advance, for permanent additional load along with conversion from single phase to three phase supply. Since the petition is found not maintainable before this Forum, the case is remanded to the AE for arranging a fresh hearing with the observations of the Ombudsman.
Penalty imposed by the CGRF against the employees of the Licensee for their lapses - P/267/2012 – Bency John, AE and Manoj Mathew, AE, KSEB

Download 
Download

The appellants are the employees of KSEB and the consumer has raised some allegations against them among other things in a petition filed before CGRF. The CGRF has ordered to refund the excess amount collected from the petitioner from the pockets of the appellants. A review petition filed by the employees before the CGRF was disposed of without hearing them. The appellants approached Hon High Court and it was directed to hear the case by this Authority. It is held that the Board may refund the excess amount collected, since the same lie with KSEB A/C and also directed to pay litigation cost by the appellants.
Disconnection of electric connection of the employee’s quarters by the Licensee – P/299/2012 – Mani C, Munnar.

Download 
Download

The Distribution Licensee of electricity in the Munnar area was the employer of the appellant. Due to a labour dispute, the licensee tried to evict the appellant from the quarters of the employer and he disconnected electric connection without a notice. An industrial dispute raised by the appellant is still pending in the court and the appellant has obtained an injection order against forceful eviction from the company quarters. It is ordered to give reconnection of the electric supply to the appellant’s quarters within 24 hours.

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday1973
mod_vvisit_counterAll6232851