KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
![]() |
![]() |
![]() |
![]() |
Category: Orders | ||
![]() |
Files: 1327 | |
Orders of Kerala Electricity Ombudsman in pdf format |
![]() ![]() |
|
The appellant Shri.C.P Prabhakumar is the owner of the Coastal Breeding Farm (Pvt.) Ltd. at Vannamada, Palakkad with Consumer no. 1165020021296. The said connection was taken as a temporary in LT VII A tariff for the construction purpose with connected load 6.89KW in the name of Mr. Ramakrishnan which was connected on 29/04/2013. Later the connection was changed with the appellant, as 3 phase LT, with connected load 44.459 KW with contract demand of 20 KWA. The tariff applied was changed from LT 7A to LT 4A as per the request of the consumer on 10/01/2014. The appellant was running a duck hatchery and produce day old duckling and selling outside. The certificate issued by the District Industries Centre states that the industry is Hatchery. The Licensee issued by Eruthempathy Panchayath as well as in Kerala State Pollution Control Board also states that the unit is Hatching the Duck egg and produces daily one ducklings. The Licensee had applied the tariff LT IV A, and latter changed into LT V B based on the request of the consumer and conducting inspection on 06/08/2023. The allegation of the appellant is that the Licensee would have applied the tariff since 10/01/2014. Itself, Or would have changed by the Licensee on suo motto as per regulation 97 of the Supply Code, 2014. The appellant had filed the petition to the CGRF and CGRF in order on completing the procedures on 11.11.2024. The Aggrieved the appellant had filed this petition as appeal to the order of CGRF. |
![]() ![]() |
|
The appellant Shri. Denny Simon is a domestic consumer with Consumer no.1156565001346 and with connected load 8.426 KW. The appellant had applied for solar connection on 02/03/2024 and the solar plant was commissioned on 12/04/2024. When the solar plant was connected the billing pattern has been changed to the monthly billing from the previous bimonthly billing. The date of last reading was 04/04/2024 which was before solar panel connection. The period from 04/04/2024 to 12/04/2024 was the non solar period consumption. The next bill issued on 02/05/2024 in which 04/04/2024 to 12/04/2024 is the non solar period and for the period from 12/04/2024 to 02/05/2024 was the solar period. The bill so issued amounts to Rs. 550.70/- for solar period at Rs. 207.28 for the solar period totaling to Rs.758/-. The reading for a period from 04/04/2024 to 12/04/2024 was 68 units. 68 units were consumed for 8 days then the monthly consumption was arrived and this exceeds 250 units and accordingly the flat rate tariff @ Rs. 6.4/- per unit was applied. The appellant challenged this method of calculation. His argument is the total consumption was only 68 units and the tariff applied should be telescopic tariff applicable to 68 units. The appellant filed the petition to CGRF and CGRF issued order on 03/12/2024.Aggrieved with the order of the CGRF, the appellant had filed this appeal petition to this Authority. |
![]() ![]() |
|
The appellant is Shri. Sajan Varghese, Director of M/s.Saj Flight Services (P) Ltd., Thiruvananthapuram, and represented by Shri. Reji Varghese. M/s. Saj Flight Services is a dismantled HT Consumer under the Electrical Section Sreevaraham which is coming under the jurisdiction of Deputy Chief Engineer, Electrical Circle, Thiruvananthapuram. The service connection was disconnected on 01/02/2014 and dismantled on 16/08/2015. The arrear energy charges at the time of dismantling was not paid and hence revenue recovery action was initiated to recover the current charge dues. The energy charges were not paid for a period from 02/2012 to 09/2013 and the amount pending as on 07/2016 was Rs. 3,04,771 which include the principal amount of Rs.2,07,053 and interest Rs.97,718/-. An amount Rs 1,26,73 of is under dispute as the Licensee had filed writ petition to Hon’ble High Court fo Kerala against the order of State Electricity Ombudsman dated 21/01/2009 regarding the reduction of contract demand for a period from 11/2005 to 01/2008. The revenue recovery action is intiated for the undisputed amount with interest. The appellant is contenting the revenue recovery proceedings and filed the petition to CGRF.CGRF issued order dated 10/11/2024 on completing the proceedings. Aggrieved by the decision of CGRF, this appeal petition is filed to this Authority. |
KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488
Send an email to info@keralaeo.org
![]() | Today | 2932 |
![]() | All | 6256464 |
P/021/2025, Smt. Daisamma George |
02-05-2025 |
P014/2025, Smt. Chitra Nair |
02-05-2025 |
P/013/2025, Sri.Sabu Johny |
02-05-2025 |
P/012/2025,Sri.Mohammed Ibrahim |
02-05-2025 |
P/011/2025, Sri.Satheesh Kumar |
02-05-2025 |
P/010/2025, Sri. Satheesh Kumar |
02-05-2025 |
P/09/2025, Sri.B.R.Ajith |
02-05-2025 |
P/08/2025, Sri.Mohammed Kabeer |
02-05-2025 |
P/07/2025, Sri.P.R.Gireesan |
04-04-2025 |
P/06/2025, Sri. Sajan.Varghese |
04-04-2025 |