Downloads
Overview Search Downloads Submit file Up
Category: Orders
Page 10 of 433
Order by: Default | Name | Date | Hits | [Descending]
Orders Files: 1297
Orders of Kerala Electricity Ombudsman  in pdf format
Files:
P/040/2024/Shri.K.P.Poulose

Download 
Download

The appellant Shri. K.P.Poulose is a domestic consumer of the licensee (KSEBL) under the Electrical section, Meenangadi with tariff LT.1A. The appellant was having a domestic connection for his residence and availed another connection under tariff LT 1A for labour shed near to his home. The consumer number is 1165935040166 and connected on 24/03/2023 and the registered connected load is 1087 watts. APTS along with the officials of the electrical section conducted an inspection on 07/02/2024 and found that two connections in the same tariff in same premises is against the regulation. And also seen that nobody is residing this shed instead the power is utilized for charging the Electric Vehicle (EV) of the inmates of the house (main house). This domestic connection was not used for any residential purpose and no laboures were residing this shed. EV charging by availing another domestic connection is the violation of regulation. Accordingly the licensee has issued a demand notice calculating energy charges adding both the consumptions and reducing the amount already paid. This amount worked out to Rs. 12,293/-. The appellant contented the demand and filed the petition to CGRF. CGRF issued order dated 18/05/2024 stating that the appellant is liable to pay the short assessment bill. Aggrieved by the decisions of CGRF, this appeal petition is field to this Authority.
P/045/2024, Shri. Sabu Johny

Download 
Download

he appellant Shri. Sabu Johny the Managing Director of EVM Passenger Cars Pvt Ltd Thiruvalla is a commercial consumer of the Licensee KSEBL.The consumer number is 1146408017269 and connected load was 79 Kw under LT 7 A tariff. The appellant requested the licensee to enhance the connected load to 132 Kw on 16/06/2023 and also opted for demand based tariff with contract demand of 70 KvA. The application fee was remitted on 25/07/2023. On site inspection it is noted that the transformer was overloaded and hence not feasible to enhance the connected load to 132 Kw. The load enhancement could be possible either by installing a separate transformer or enhancing the capacity of the existing transformer. A demand notice has been send to the appellant for Rs.5,12,655/- including the cost of a new 100 KvA transformer for the first option. Another estimate of Rs. 3,18,555/- has also been intimated for enhancing the capacity of the existing transformer. The consumer has been intimated that there is a chance to exceeded the maximum demand than the contracted demand which will overload the system. The appellant approached CGRF and CGRF ordered that the respondent is directed to execute the work after the appellant remitting the estimate amount. Aggrieved with the decision the appellant filed this appeal petition. Subsequent on submission of appeal the appellant submitted the letter stating that the petition is withdrawn as the respondent has complied with the requirement.
P/042/2024, Shri. Mohammed M.P, Kozhikode

Download 
Download

The appellant Shri. Mohammed M.P is a consumer of the licensee under their Section Electrical section, Balusserry with consumer number 1166138041578. The three phase service connection under the tariff LT.7A with connected load 39.928 Kw was connected on 16/01/2018. The power is availed for the working of a Gold and Jewellery shop named as ‘M/s. Diya Gold and Diamonds’. Anti Power Theft Squad (APTS) conducted an inspection on 09/11/2023 and found that B phase current was recorded zero by the meter. This is only because of the B phase terminal of ‘CT’ is not connected to the meter terminal. The meter was recorded 2/3rd of the actual consumption and the fault occurred since 06/03/20218 and the same was rectified on 27/11/2023. After the rectification the meter started recording the actual consumption. The site mahazar was prepared and a copy was landed over to the representative of the consumer. The licensee was prepared the bill for the short assessment for Rs. 11,19,440/- and send as demand notice. The appellant filed the petition to CGRF and CGRF has ordered to revise the short assessment calculating the average consumption before and after the rectification. Accordingly the short assessment has been revised to Rs. 6,35,437/-. The CGRF ordered that the appellant is liable to pay the amount as per the revised short assessment bill. Aggrieved by the decision of CGRF, this appeal petition was filed to this Authority.

Contact Us

KERALA ELECTRICITY OMBUDSMAN
D.H. Road & Foreshore Road Junction,
Near Gandhi Square,
Ernakulam, Kerala-682 016
Ph: 0484 2346488, Mob: 8714356488

Any Queries?

Send an email to info@keralaeo.org

Do you Know?

Consumers should submit  petitions to CGRF first before appealing Ombudsman.

Visitors Counter

mod_vvisit_counterToday103
mod_vvisit_counterAll5670345